Sample Pit: September 2026

Worked out from the downtime your supervisors recorded. Nobody typed an hour meter reading.

The month

2030.3 hours digging out of 2100 available. 69.7 hours lost across 75 delays. 5.3 hours of that hanging.

That is 533 loads not moved, at 140 BCM a load.

EX63 lost the most: 14.1 hours over 25 shifts.

Lost time per dig unit

Machine Shifts Digging h Lost h Hanging h BCM/h Loads not moved
EX63 25 285.9 14.1 2.2 h 873 measured 88 loads
EX21 25 287.4 12.6 0.9 h 1,490 measured 134 loads
EX07 25 288.1 11.9 1.3 h 1,160 measured 99 loads
EX44 25 288.1 11.9 0.9 h 1,257 measured 107 loads
EX12 25 295.4 4.6 0 1,250 measured 41 loads

Lost time per ROM loader

Machine Shifts Digging h Lost h Hanging h BCM/h Loads not moved
LD22 25 285.4 14.6 0 620 target 65 loads
LD08 25 300 0 0 620 target 0 loads

What the delays were

Feeder blockage cleared 14.6 h 21% of it
Fitters on site 10.8 h 15% of it
Blast clearance 9.5 h 14% of it
Waiting on the shot 9.3 h 13% of it
Ground engaging tools 7.7 h 11% of it
Stood down in the wet 5.5 h 8% of it
Gapping, short on trucks 4.9 h 7% of it
Hydraulic hose 3.7 h 5% of it
Stood down in the wet, whole pit 1.2 h 2% of it
Track tension 0.9 h 1% of it
Hydraulic hose on the stick, fitters on site 0.8 h 1% of it
Ground engaging tools, two teeth replaced 0.6 h 1% of it
Gapping, three trucks down at the workshop 0.4 h 1% of it

5 weeks counted. A week belongs to the month its Monday falls in. Shown as loads rather than dollars, because this site has given us what its machines average an hour and not what it is paid a BCM. Lost hours times that average, and nothing else in it. Give us the rate per BCM and the same figures carry a dollar. Where a machine shows a measured rate it comes from your own load count at 140 BCM a load, before survey reconciliation. A machine showing a target rate is costed at what the site asks of it. Counted from signed handovers. The handovers themselves are deleted on the site's retention window; these totals are what is kept.